Question 41

Multiple Choice

A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?


A) Reduced quality
B) Reduced scope
C) Reduced risk
D) Reduced timeline

Correct Answer: