Multiple Choice
The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project. Which of the following changes would BEST satisfy the project sponsor?
A) Add the project sponsor to all project email correspondence moving forward
B) Include the project sponsor in all project meetings moving forward
C) Add a new line to the communications plan to provide a weekly status report with a dashboard
D) Include the project sponsor in the daily stand-up with the entire project team
Correct Answer:

Verified
Correct Answer:
Verified
Q34: A company was originally organized using a
Q35: A project manager is assigned to an
Q36: The project team has identified all the
Q37: A vendor is late with product deliverables.
Q38: The government wants to start a project
Q40: A project encountered a problem and reached
Q41: A company hires a number of interns
Q42: A company purchased a parachute supplier and
Q43: Which of the following is a reason
Q44: A project manager is performing resource leveling