Solved

Which of the Following Methods Should a Project Manager Use

Question 14

Multiple Choice

Which of the following methods should a project manager use to improve email communication for a time-sensitive, high-visibility global project? (Choose two.)


A) Limit email recipients to only required team members.
B) Increase the number of emails to encourage team interaction.
C) Set up emails with bold text and all caps in the subject line.
D) Eliminate acronyms from the email to avoid miscommunication.
E) Include more information to increase the length of each email message.
F) Include detailed technical consideration in each email.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions