Multiple Choice
The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit. Which of the following actions should the project manager take?
A) Initiate change control.
B) Follow communications plan.
C) Manage project quality.
D) Prepare a performance report.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: A project team is not delivering their
Q5: A PM has a complex project that
Q6: During the testing phase, a team member
Q7: Two highly skilled resources, who are currently
Q8: The key stakeholders have reported the project
Q10: Which of the following is a component
Q11: A project's stakeholders have not been informed
Q12: A project manager has noticed poor attendance
Q13: The project manager has noticed a vendor
Q14: Which of the following methods should a