Multiple Choice
A project's stakeholders have not been informed of project updates and milestones by the CCB and project team. The stakeholders have threatened to withdraw project support. Which of the following should the project manager do to get buy-in from the stakeholders for the project?
A) Update the communications plan to include the stakeholders
B) Expedite completion of the project before support is withdrawn by the stakeholders
C) Revise the quality management plan to include the project stakeholders
D) Increase the number of status reports provided to the project stakeholders
Correct Answer:

Verified
Correct Answer:
Verified
Q6: During the testing phase, a team member
Q7: Two highly skilled resources, who are currently
Q8: The key stakeholders have reported the project
Q9: The business stakeholder has been engaged late
Q10: Which of the following is a component
Q12: A project manager has noticed poor attendance
Q13: The project manager has noticed a vendor
Q14: Which of the following methods should a
Q15: A fire occurred in the production facility
Q16: A project manager is procuring new equipment