Multiple Choice
A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?
A) Issue log
B) Status report
C) Risk register
D) SOW
Correct Answer:

Verified
Correct Answer:
Verified