Multiple Choice
A project team is showing off a new product prototype at a trade show, and potential customers are requesting more information. Which of the following is the MOST efficient way to provide more information?
A) Printed media
B) Email
C) Meeting
D) Video conference
Correct Answer:

Verified
Correct Answer:
Verified