Multiple Choice
A customer is in the early planning stages of a technology rebuild. To gain a better understanding of the possible solutions, which of the following documents should the customer send to prospective vendors?
A) RFP
B) RFQ
C) RFI
D) SOW
Correct Answer:

Verified
Correct Answer:
Verified