Multiple Choice
A Chief Executive Officer (CEO) has approached a project team member to request a project change. Which of the following would be the BEST step for the project manager to take to prevent scope creep?
A) Deny the CEO's request.
B) Implement the project change.
C) Submit the request to the CCB.
D) Ask the CEO to follow the communications plan.
Correct Answer:

Verified
Correct Answer:
Verified