Multiple Choice
There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed. Which of the following project management tools would help?
A) Issue log
B) Project charter
C) Dashboard
D) Meeting minutes
Correct Answer:

Verified
Correct Answer: