The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation. Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
A) The issue log to show why the vendor should be replaced.
B) The team action items to show why the vendor should be replaced.
C) The scope statement to show why the vendor should be replaced.
D) A procurement plan to show why the vendor should be replaced.
E) A change management plan to have the vendor replaced.
Correct Answer:

Verified
Correct Answer:
Verified
Q331: A project team has determined it will
Q332: Using Scrum, which of the following are
Q333: A stakeholder informs a project manager that
Q334: Which of the following defines the minimum
Q335: There is a project in which the
Q337: Which of the following is the MOST
Q338: The client accepts the critical design review.
Q339: Which of the following resources outlines consequences
Q340: A project manager wants to introduce the
Q341: A project manager is scheduling activities and