Multiple Choice
A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO) .
A) Using the WBS will help prevent work from slipping or being forgotten.
B) TheWBS will be required on very large projects.
C) TheWBS will be required if the project manager has the time available to complete it.
D) TheWBS will aid in determining which resources are required for the project.
E) The WBS is the best way to determine risks of the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q335: There is a project in which the
Q336: The project manager was asked to provide
Q337: Which of the following is the MOST
Q338: The client accepts the critical design review.
Q339: Which of the following resources outlines consequences
Q341: A project manager is scheduling activities and
Q342: A carpenter on a project team reports
Q343: A customer has requested a new feature
Q344: The project manager for a TV tower
Q345: A project sponsor approaches the project manager