Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
Use this information to answer the following questions. Consider the following Activity-On-Node (AON) project (activity completion times are in days) .    -Refer to the figure.What is the slack time,in days,associated with activity E? A) 1 B) 2 C) 0 D) 3 E) 4
-Refer to the figure.What is the slack time,in days,associated with activity E?


A) 1
B) 2
C) 0
D) 3
E) 4

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions