Multiple Choice
Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity's completion time (in days) correspond to an optimistic time,most likely time,and pessimistic time,respectively.
-Refer to the figure.What is the probability of not completing the project within 18 days?
A) 0.0668
B) 0.4332
C) 0.9332
D) 0.4878
E) 0.0122
Correct Answer:

Verified
Correct Answer:
Verified