Use This Information to Answer the Following Questions -Refer to the Information Above

Question 25

Essay

Use this information to answer the following questions.
Consider the following set of activities that must be completed in order to prep a new home for painting.
 Immediate  Activity  Predecessors  A  B  C  A, B  D  C  E  C  F  D, E  G  E  H  F, G \begin{array}{cl} & \text { Immediate } \\\text { Activity } & \text { Predecessors } \\\hline \text { A } & - \\\text { B } & - \\\text { C } & \text { A, B } \\\text { D } & \text { C } \\\text { E } & \text { C } \\\text { F } & \text { D, E } \\\text { G } & \text { E } \\\text { H } & \text { F, G }\end{array}

-Refer to the information above.Assume that the painters were able to estimate the activity times as shown in the table below.
 Activity  Time (Days)  A 3 B 2 C 4 D 5 E 3 F 2 G 4 H 2\begin{array} { c l l } \text { Activity } & \text { Time (Days) } \\\text { A } & 3 \\\text { B } & 2 \\\text { C } & 4 \\\text { D } & 5 \\\text { E } & 3 \\\text { F } & 2 \\\text { G } & 4 \\\text { H } & 2\end{array}
a.Calculate the slack for each activity.
b.Calculate the earliest and latest start and finish times for each activity.
c.Determine the critical path.
d.Determine the length of the project.