Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
Use this information to answer the following questions. Consider the following Activity-On-Node (AON) project (activity completion times are in days) .    -Refer to the figure.What is the earliest start time (EST) and earliest finish time (EFT) of activity E? A) EST = 7,EFT = 10 B) EST = 10,EFT = 7 C) EST = 11,EFT = 8 D) EST = 8,EFT = 10 E) EST = 8,EFT = 11
-Refer to the figure.What is the earliest start time (EST) and earliest finish time (EFT) of activity E?


A) EST = 7,EFT = 10
B) EST = 10,EFT = 7
C) EST = 11,EFT = 8
D) EST = 8,EFT = 10
E) EST = 8,EFT = 11