Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
Use this information to answer the following questions. Consider the following Activity-On-Node (AON) project (activity completion times are in days) .    -Refer to the figure.What is the critical path? A) ABDF B) ABEF C) ACDF D) ACEF E) none of the above
-Refer to the figure.What is the critical path?


A) ABDF
B) ABEF
C) ACDF
D) ACEF
E) none of the above