Solved

Use This Information to Answer the Following Questions

Question 44

Multiple Choice

Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity's completion time (in days) correspond to an optimistic time,most likely time,and pessimistic time,respectively.
Use this information to answer the following questions. Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity's completion time (in days) correspond to an optimistic time,most likely time,and pessimistic time,respectively.    -Refer to the figure.What is the standard deviation associated with the completion time of activity B? A) 0.1111 B) 0.2222 C) 0.3333 D) 2 E) 5
-Refer to the figure.What is the standard deviation associated with the completion time of activity B?


A) 0.1111
B) 0.2222
C) 0.3333
D) 2
E) 5

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions