Multiple Choice
Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
-Refer to the figure.Determine the latest start time (LST) and latest finish time (LFT) of activity B.
A) LST = 9,LFT = 5
B) LST = 5,LFT = 9
C) LST = 8,LFT = 4
D) LST = 4,LFT = 8
E) LST = 8,LFT = 10
Correct Answer:

Verified
Correct Answer:
Verified