Multiple Choice
Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity's completion time (in days) correspond to an optimistic time,most likely time,and pessimistic time,respectively.
-Refer to the figure.What deadline should be set to ensure a 99% probability that the project will be completed within the deadline date?
A) 19.45 days
B) 19 days
C) 18 days
D) 20.56 days
E) 18.54 days
Correct Answer:

Verified
Correct Answer:
Verified