Solved

Use This Information to Answer the Following Questions -Refer to the Information Above

Question 2

Essay

Use this information to answer the following questions.
Jamie is planning a trip overseas.A variety of activities must be completed before her departure.The following table describes the relationships between these activities.
 Immediate  Activity  Predecessors  A  B  A  C  A  D  B, C  E  B, C  F  D, E  G  F \begin{array} { c l } & \text { Immediate } \\\text { Activity } & \text { Predecessors } \\\text { A } & - \\\text { B } & \text { A } \\\text { C } & \text { A } \\\text { D } & \text { B, C } \\\text { E } & \text { B, C } \\\text { F } & \text { D, E } \\\text { G } & \text { F }\end{array}
-Refer to the information above.Jamie was able to estimate the activity times as shown in the table below.
a.Calculate the earliest and latest start and finish times for each activity.
 Activity  Time (Days)  A 4 B 4 C 5 D 3 E 3 F 2 G 1\begin{array} { c l l } \text { Activity } & \text { Time (Days) } \\ \text { A } & 4 \\\text { B } & 4 \\\text { C } & 5 \\\text { D } & 3 \\\text { E } & 3 \\\text { F } & 2 \\\text { G } & 1\end{array}
b.Calculate the slack for each activity.
c.Determine the critical path.
d.Determine the length of the project.

Correct Answer:

verifed

Verified

Related Questions