Use the Project Below

Question 30

Essay

Use the project below.
Use the project below.    a. How long is the critical chain?  b. How long is the project buffer? c. Given the task status updates in the table below, fill in the rest of the table    d. Based upon the percent CC consumed and percent buffer consumed as if week 16, can the project be completed within the CC + project buffer time? Please be specific. a. How long is the critical chain?
b. How long is the project buffer?
c. Given the task status updates in the table below, fill in the rest of the table
Use the project below.    a. How long is the critical chain?  b. How long is the project buffer? c. Given the task status updates in the table below, fill in the rest of the table    d. Based upon the percent CC consumed and percent buffer consumed as if week 16, can the project be completed within the CC + project buffer time? Please be specific. d. Based upon the percent CC consumed and percent buffer consumed as if week 16, can the project be completed within the CC + project buffer time? Please be specific.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions