Multiple Choice
Issue management: circle all statements below that are true:
A) Is the practice of identifying in the definition phase of the project all potential issues and addressing them in the project plan
B) Addresses any emerging problem, risk, or change in the project that must be resolved
C) Refers to identifying and managing issues as they emerge throughout the project
D) Is exactly the same as risk management
E) Refers to keeping tracking of the version or release number of a product
F) In a typical project can be handled informally and requires no documentation.
G) Issues have little bearing on project completion since, often, they can be resolved after the project has been closed-out.
Correct Answer:

Verified
Correct Answer:
Verified
Q24: Statement: The concept of earned value is
Q25: Match the following formulas with their appropriate
Q26: Statement: Quality control methods in projects seek
Q27: In controlling projects, data on actual project
Q28: Work progress should be reviewed (circle all
Q30: Use the project below.<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TBR1472/.jpg" alt="Use
Q31: Statement: The tendency for a project to
Q32: Activity X has four immediate predecessors, three
Q33: Match the following formulas with their appropriate
Q34: Statement: Configuration management refers largely to the