Multiple Choice
Howard's program, Ferocious, has been well-received at his company. Now, he needs to create a program charter. Which of the following will not be included in Howard's program charter to launch Ferocious?
A) Key objectives
B) List of high-level executives who will be involved in program planning
C) Expected benefits the program will deliver
D) The program vision