David is the program manager of the Make It Look Good program, which is in the planning stage. David isn't certain if items should be purchased or produced in-house. Which process should David perform to decide?


A) Procurement Planning
B) Plan Program Contracting
C) Risk Management Planning
D) Plan Program Purchases and Acquisitions