Multiple Choice
Howard is creating a program WBS hierarchy for his program, Ferocious. Which of the following components is at the lowest level of his hierarchy?
A) Schedule activities
B) Program deliverables
C) Program packages
D) Work packages
Correct Answer:

Verified
Correct Answer:
Verified