Multiple Choice
Brendan is managing a large IT project at a venture-backed startup that is scaling up. The project requires frequent change requests due to multiple IT initiatives simultaneously happening within the growing firm. A particular business manager with a lot of clout is pressing Brendan to make changes that may not only impact the project's scope, but cost and timeline as well. Which exemplifies the best route for Brendan to take?
A) He could use corrective action.
B) He could suggest the formation of a change control board.
C) He could employ dynamic programming.
D) He could hold a kickoff meeting.
E) He could consult the scope creep committee.
Correct Answer:

Verified
Correct Answer:
Verified
Q158: Which is NOT an input to the
Q159: For which of the following should you
Q160: Moris Lipswitch, the program sponsor, is asking
Q161: Howard is creating a program WBS hierarchy
Q162: Finnian is the program manager of a
Q164: Integration Management includes which program Planning processes?<br>A)Develop
Q165: Which is NOT an input to the
Q166: Sonia Hedgeswine's program, Spin Spin Spin, is
Q167: Which is NOT an input to the
Q168: What is the main difference between project