Moris Lipswitch, the program sponsor, is asking for the performance measurement baseline. Which of the following are three components of a performance measurement baseline?


A) Cost baseline, quality baseline, and scope baseline
B) Cost baseline, schedule baseline, and risk baseline
C) Scope baseline, cost baseline, and timeline
D) Scope baseline, schedule baseline, and cost baseline

Correct Answer: