Multiple Choice
The CPI of project is .90, and the EV is $90,000. How much money has actually been spent on the project?
A) $100,000
B) $81,000
C) $810,000
D) $99,000
E) $98,100
Correct Answer:

Verified
Correct Answer:
Verified