Solved

When Is the Project Manager Using Parametric Estimation

Question 8

Multiple Choice

When is the project manager using parametric estimation?


A) If the Project Manager is using his instinct to determine the estimated project length
B) If the Project Manager needs to pad their estimates
C) If the Project Manager is using Monte Carlo analysis
D) Using a statistical relationship that exists through historical data or other mathematical relationship
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions