Solved

When Is the Project Manager Using Analogous Estimating

Question 12

Multiple Choice

When is the project manager using analogous estimating?


A) The PM doesn't have all of the information needed to give time estimates
B) The PM needs to pad their estimates
C) The PM is using a mathematical model
D) The PM uses similar projects or activities to assist with time estimates
E) The PM is using a Monte Carlo technique

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions