Multiple Choice
When is the project manager using analogous estimating?
A) The PM doesn't have all of the information needed to give time estimates
B) The PM needs to pad their estimates
C) The PM is using a mathematical model
D) The PM uses similar projects or activities to assist with time estimates
E) The PM is using a Monte Carlo technique
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Finn's boss asked him to put together
Q8: When is the project manager using parametric
Q9: The CPI of project is .90, and
Q10: Michael is looking at a network diagram
Q11: Lance Uppercut has been on the job
Q13: What does the 50/50 rule of progress
Q14: This is based on a real scenario
Q15: What is a murder board? Select all
Q16: What is true of corrective action?<br>A)Action against
Q17: What does the 20/80 rule of progress