Multiple Choice
Which of the following is NOT a PRINCE2 process?
A) Directing a Project
B) Assessing a Project
C) Controlling a Stage
D) Closing a Project
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q26: Follow on action recommendations are made in
Q27: Which process triggers the request to deliver
Q28: Which of the following is NOT true
Q29: Which of the following products are part
Q30: When authorising a project the Project Board
Q32: Which of the following attributes should the
Q33: Which of the following documents is NOT
Q34: At what point is the Stage Plan
Q35: To which section of the Quality Management
Q36: Which of the following activities does PRINCE2