Which of the Following Is NOT True for a PRINCE2

Question 28

Multiple Choice

Which of the following is NOT true for a PRINCE2 Plan?


A) It describes how a specific target is to be achieved.
B) It includes timescales and benefits for the defined targets.
C) It contains sufficient information to confirm the targets are achievable.
D) It includes named resources responsible for achieving the target.

Correct Answer: