When Authorising a Project the Project Board Must Confirm

Question 30

Multiple Choice

When authorising a project the Project Board must confirm:
1) A suitable Business Case exists and shows a viable project
2) Suitable resources have been assigned to support the Project Plan
3) The projects strategies and controls support delivery of the Project Plan
4) The Project Plan is adequate to deliver the Business Case


A) 1, 2, 3
B) 1, 2, 4
C) 1, 3, 4
D) 2, 3, 4