Question 28

Question 28

Multiple Choice

What term is used for the process whereby a risk within an individual project can be referred to the programme for management?


A) Sharing
B) Escalation
C) Transfer
D) Absolution

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q23: Which of the following is NOT within

Q24: Which of these would you NOT find

Q25: Which of the following documents does NOT

Q26: Which of the following should not be

Q27: Which of the following is a key

Q29: For a programme that focuses on technology

Q30: Which of the following should NOT be

Q31: Which of the following is NOT one

Q32: What is the name of the relational

Q33: In which document are project risk escalation

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines