Multiple Choice
Which of these would you NOT find in a Risk Management Strategy?
A) Scales for estimating probability
B) The identification of risk actionees
C) Relevant early-warning indicators
D) Guidance on how proximity for risks is to be assessed
Correct Answer:

Verified
Correct Answer:
Verified