Multiple Choice
Which of the following should not be part of the Programme Plan?
A) Project timescales, costs, outputs, and deliverables
B) Transition plans
C) Monitoring and control activities and performance targets
D) The detailed schedules for every project in the dossier
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q21: In which part of Transformational Flow would
Q22: When are programmes normally closed?<br>A)When all projects
Q23: Which of the following is NOT within
Q24: Which of these would you NOT find
Q25: Which of the following documents does NOT
Q27: Which of the following is a key
Q28: What term is used for the process
Q29: For a programme that focuses on technology
Q30: Which of the following should NOT be
Q31: Which of the following is NOT one