    The Expected Out Turn of Cement Concrete 1 : 2
Solved

The Expected Out Turn of Cement Concrete 1 : 2

Question 9

Question 9

Multiple Choice

The expected out turn of cement concrete 1 : 2 : 4 per mason per day is


A) 1.5 m3
B) 2.5 m3
C) 3.5 m3
D) 5.0 m3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: Pick up the correct statement in case

Q5: The trap which is provided to disconnect

Q6: Anti-siphonage pipe is connected to<br>A)main soil pipe<br>B)bottom

Q7: The area is measured correct to the

Q8: Pick up the correct statement from the

Q10: The measurement is not made in square

Q11: Pick up the correct statement from the

Q12: In long and short wall method of

Q13: The concrete work for the following part

Q14: While preparing a detailed estimate<br>A)dimension should be

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines