Solved

The Table Below Shows the Tasks Required to Complete a Project

Question 25

Multiple Choice

The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Which of the following tasks has a non-zero slack? The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Which of the following tasks has a non-zero slack?   A) A B) B C) D D) F E) C


A) A
B) B
C) D
D) F
E) C

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions