Multiple Choice
A lean system has the following characteristics: demand rate = 40 parts per hour; safety stock required = 10%; the container size = 8; lead time to replenish an order = 4 hours.
-Calculate the maximum system inventory for this part.
A) 16 units
B) 40 units
C) 240 units
D) 80 units
E) 176 units