Multiple Choice
A lean system uses 12 containers, each of which can hold 12 parts. The lead time required to round-trip one container through the system is normally 3 hours. The usual safety stock is 20%.
-Calculate the maximum system inventory for this part.
A) 36 units
B) 40 units
C) 144 units
D) 80 units
E) 480 units
Correct Answer:

Verified
Correct Answer:
Verified