Multiple Choice
Copenhagen Industries uses a kanban system to manage production of their subassembly. In a 10-hour day, they use 1,500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the subassembly line that is currently rated at a 15% safety factor.
-How many containers should the kanban system of Copenhagen Industries be using?
A) 26
B) 82
C) 155
D) 9
E) 3
Correct Answer:

Verified
Correct Answer:
Verified
Q5: The Frankenmuth Fasteners Co. was implementing lean
Q6: Lady Bug Machineries uses a lean production
Q7: A lean system has the following characteristics:
Q8: The Frankenmuth Fasteners Co. was implementing lean
Q9: An integrated electronic-chip manufacturer has a demand
Q11: The Frankenmuth Fasteners Co. was implementing lean
Q12: Lady Bug Machineries uses a lean production
Q13: An integrated electronic-chip manufacturer has a demand
Q14: Copenhagen Industries uses a kanban system to
Q15: The Frankenmuth Fasteners Co. was implementing lean