Multiple Choice
Copenhagen Industries uses a kanban system to manage production of their subassembly. In a 10-hour day, they use 1,500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the subassembly line that is currently rated at a 15% safety factor.
-If the required safety stock was changed to zero and 3 containers were being used in the system, calculate the maximum inventory.
A) 4,100 units
B) 400 units
C) 150 units
D) 5,000 units
E) 1,300 units
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Lady Bug Machineries uses a lean production
Q3: The Frankenmuth Fasteners Co. was implementing lean
Q4: The Frankenmuth Fasteners Co. was implementing lean
Q5: The Frankenmuth Fasteners Co. was implementing lean
Q6: Lady Bug Machineries uses a lean production
Q7: A lean system has the following characteristics:
Q8: The Frankenmuth Fasteners Co. was implementing lean
Q9: An integrated electronic-chip manufacturer has a demand
Q10: Copenhagen Industries uses a kanban system to
Q11: The Frankenmuth Fasteners Co. was implementing lean