Multiple Choice
Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system.
-Calculate the maximum system inventory for this part.
A) 250 units
B) 50 units
C) 100 units
D) 200 units
E) 150 units
Correct Answer:

Verified
Correct Answer:
Verified
Q40: An integrated electronic-chip manufacturer has a demand
Q41: A lean system has the following characteristics:
Q42: Berlin Industries uses a kanban system to
Q43: Lady Bug Machineries uses a lean production
Q44: A lean system has the following characteristics:
Q46: The Frankenmuth Fasteners Co. was implementing lean
Q47: Istanbul Industries uses a kanban system to
Q48: An integrated electronic-chip manufacturer has a demand
Q49: A lean system uses 12 containers, each
Q50: Berlin Industries uses a kanban system to