The Frankenmuth Fasteners Co. was implementing lean throughout their shop floor and needed to determine the number of containers at several of their work centers. In one such work center, the demand was 200 parts per hour, and the containers they used for this part held 50 parts. It normally takes 6 hours for a full container to make a circuit through the work cell and back to its input side, and they desired to carry 12% safety stock in the system.
-If the required round-trip time were 5 hours and there were 23 containers, what would be the safety stock for the lean system?
A) 5%
B) 3.5%
C) 10%
D) 12%
E) 15%
Correct Answer:

Verified
Correct Answer:
Verified
Q40: An integrated electronic-chip manufacturer has a demand
Q41: A lean system has the following characteristics:
Q42: Berlin Industries uses a kanban system to
Q43: Lady Bug Machineries uses a lean production
Q44: A lean system has the following characteristics:
Q45: Lady Bug Machineries uses a lean production
Q47: Istanbul Industries uses a kanban system to
Q48: An integrated electronic-chip manufacturer has a demand
Q49: A lean system uses 12 containers, each
Q50: Berlin Industries uses a kanban system to