Multiple Choice
Assume a facility is open 8 hours a day and requires an output of 600 units a day. The following tasks must be arranged as an assembly line:
-Considering there are 4 work centers for the assembly line, what is the efficiency?
A) 78.13%
B) 62.50%
C) 52.08%
D) 100%
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified