Multiple Choice
The process design team at a contract manufacturer in Thailand has broken an assembly process into 8 basic steps, each with a required time and predecessor, as shown in the table. There are 7.5 productive hours available in a day, and the manufacturer wishes to produce 400 units.
-The managers decide to balance the line by assigning tasks to workstations to fill up as much task time as possible. Break ties by assigning the longest task first. What task(s) should be assigned at the third workstation?
A) D
B) B, E
C) F
D) C, E, and G
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified
Q56: Use the Cluster-first-route-second heuristic for two trucks
Q57: Assume a facility is open 8 hours
Q58: Use the Clark and Wright savings heuristic
Q59: Assume a facility is open 8 hours
Q60: Assuming that the customers are ranked in
Q62: A tier-two supplier needs to produce 300
Q63: Assuming that the customers are ranked
Q64: ADAMS Electricals has decided to analyze the
Q65: For the Buehler Bakery, the desired output
Q66: The following is a sketch of process-focused