Solved

A Tier-Two Supplier Needs to Produce 300 Coffee Pots Per

Question 40

Multiple Choice

A tier-two supplier needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to produce a coffee pot have been identified, timed in seconds, and ordered as indicated in the table.
A tier-two supplier needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to produce a coffee pot have been identified, timed in seconds, and ordered as indicated in the table.    -What should their takt time be? A) 96 seconds B) 90 seconds C) 80 seconds D) 60 seconds E) Need more information to answer the question
-What should their takt time be?


A) 96 seconds
B) 90 seconds
C) 80 seconds
D) 60 seconds
E) Need more information to answer the question

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions