Multiple Choice
For the Buehler Bakery, the desired output for a 8 hour workday is 450 units. The discrete tasks required to produce the product have been identified, timed in seconds, and ordered as indicated in the table.
-Considering there are 7 work centers for the assembly line, what is the efficiency?
A) 50.63%
B) 9.6%
C) 90.40%
D) 100%
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified