Multiple Choice
The rate of production the business was designed to accommodate on a long-term basis is referred to as:
A) Actual output
B) Effective capacity
C) Design capacity
D) Protective capacity
E) Overloading capacity
Correct Answer:

Verified
Correct Answer:
Verified